Artemis Gold Q1 Update: Progress on Blackwater Mine Construction

kent-jackson by kent-jackson
April 25, 2024
in News
0
Artemis Gold Q1 Update: Progress on Blackwater Mine Construction
74
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

You might also like

Couple accused of scamming $4 million from women in supposed gold mine ownership scheme, authorities report

West Red Lake Gold Announces Latest News on Madsen Mine Reopening

Today’s Gold and Silver Prices as of 31-10-2024: Find the Latest Rates in Your City

Project remains fully funded, on schedule, approximately 73% complete, within guidance for initial capital expenditure, and is advancing operational readiness

TSXV: ARTG

VANCOUVER, BC, April 24, 2024 /CNW/ – Artemis Gold Inc. (TSXV: ARTG) (“Artemis Gold” or the “Company”) provides an update on Q1 construction progress at the Blackwater Mine in central British Columbia. The project remains fully funded, within the guidance for initial capital expenditure, and on schedule for first gold pour in H2 2024.

At March 31, 2024 overall construction was approximately 73% complete, and approximately C$523 million of the guided initial capital expenditure of C$730 to C$750 million had been spent. By the end of Q1 2024, the Company had entered into contractual commitments for C$682 million (or 93% of the lower end of the guided initial capital expenditure). The majority of uncommitted expenditures relate to owners’ cost and earthworks associated with mining pre-strip and construction of the tailings storage facility and other civil structures.

Steven Dean, Chairman and CEO of Artemis Gold, stated: “We have an exceptional team managing the development of the Blackwater Mine. Execution is critical in all projects, and managing the day-to-day challenges that arise in building a mine of this scale and complexity is key to being successful. We have an experienced group of people who are first class problem solvers, ensuring we advance toward operational readiness and remain on track for first gold pour in H2 2024.

“The remainder of 2024 will be transformational for Artemis Gold as we progress the Blackwater Mine, a tier one asset in a tier one jurisdiction, into production.”

Construction Update

Mild weather conditions in Q1 2024 provided good, early access to infrastructure areas at the Blackwater Mine. Construction of major site water management facilities, including the water management pond, the central diversion system and the Davidson Creek diversion, have been completed. Work on the tailings storage facility dam is progressing well. Initial material placement has been successfully achieved, including tying into the surrounding topography, providing for optimal productivity moving into summer.

Total major works hours worked up to March 31, 2024 surpassed 1.7 million hours with a zero LTIFR1 and an AIFR2 of 87.68.

Process Plant

At the end of March 2024, the Sedgman EPC contract work on the processing plant was approximately 84% complete overall, with engineering, design and procurement essentially complete.

Process plant construction continues to progress well, particularly within steel erection and conveyor installation. Installation of mechanical equipment within the secondary and tertiary crushing circuits, as well as the screening station, was completed during the quarter. Notable achievements throughout the period included the installation of the ball mill, intensive leach reactor and the regeneration kiln, while installation of the gravity concentrator has commenced. All major tanks have been completed, including pre-leach, carbon-in-leach, and elution, and hydrotesting is underway.

Concrete work is nearing completion with most of the major pours now completed including the primary crusher run-of-mine slab, crusher vault and ore stockpile reclaim tunnel. Erection of the reagents and mill buildings are in progress with cladding works planned to commence in April.

Electrical and instrumentation activities are scaling up, with the installation of the main electrical room in the crushing circuit area now complete.

Transmission Line

During Q1 2024 the transmission line right-of-way clearing was completed. Construction contracts were awarded, and contractors mobilized to the region. Laydown areas and camp facilities have been established and civil foundation work and structure erection commenced. All electrical conductors have been delivered to site. Poles and hardware deliveries are in progress and sequenced to support the construction schedule.

The line is being built in two parts, north and south of the Nechako River. The length of the northern section is approximately 50km and the southern section approximately 80km.

Upgrades to the BC Hydro Glenannan substation are progressing to plan. Commissioning planning with BC Hydro is advancing as planned.

Work associated with Blackwater’s 25kV power distribution network has progressed according to plan with engineering at an issued-for-construction (IFC) level, procurement complete, and most materials on site. Pole foundations are 65% completed and pole erection has commenced.

Heavy Equipment

Assembly and commissioning of the owner’s mining fleet continues to advance. Two 400-tonne hydraulic backhoe excavators, six 240-tonne rigid frame haul trucks and two large mining front-end loaders are fully assembled. The remainder of the fleet to support initial operations is on site and nearing completion. Additional units will be added to the fleet as operations ramp up.

Personnel

The Company maintained its workforce of 320 employees in Q1 2024 and the ratios of the workforce have remained consistent, approximately:

  • 20% of the team are women

  • 30% identify as Indigenous

  • 50% are from the local region, and;

  • 80% are B.C. residents.

The total Blackwater Mine workforce, including staff and contractors, surpassed 600 at the end of March.

Operational Readiness

Recruitment for the Blackwater Mine operations team commenced this quarter with the first hires starting in early Q2 2024.

A laboratory contract has been signed, and all mill reagents have been tendered, with plans to finalize the contracts in Q2 2024.

Procurement for commissioning, operations, and critical spares was completed, and the operational readiness planning commenced during the quarter.

Funding

During Q1 2024, the Company completed an additional draw of $130 million under the project loan facility, bringing the total drawn to $280 million, along with approximately C$5 million in cumulative capitalized interest at March 31, 2024.

At March 31, 2024, Artemis Gold had estimated remaining Phase 1 capital expenditures of C$207 to C$227 million. At the same date, the committed sources of funding totaled C$295 million, comprising:

  • cash and cash equivalents of C$155 million;

  • remaining drawdowns from the project loan facility of C$100 million (including approximately C$20 million of capitalized interest remaining available), and

  • a cost overrun facility of C$40 million.

In addition, the Company had 23.2 million warrants outstanding which are exercisable at C$1.08 per warrant before August 27, 2024, for anticipated proceeds of C$25 million.

Artemis Gold President and COO Jeremy Langford commented: “Looking ahead to Q2 2024, we expect to complete the construction and commissioning of the initial phase of the mining fleet, advance the tailings storage facility main dam wall, and move to the completion of the construction activity in the processing facility. At the end of Q1 2024, we remain on track for first gold pour in H2 2024.”

Video

Watch here for a Q1 project update video: https://youtu.be/JFwpIC9fFZo

Photos- April 2024

Project Plant Site – April 2024 (CNW Group/Artemis Gold Inc.)

Project Plant Site – April 2024 (CNW Group/Artemis Gold Inc.)

CIL Tanks and Processing and Reagents Buildings Installation (CNW Group/Artemis Gold Inc.)CIL Tanks and Processing and Reagents Buildings Installation (CNW Group/Artemis Gold Inc.)

CIL Tanks and Processing and Reagents Buildings Installation (CNW Group/Artemis Gold Inc.)

Ball Mill Shell and Heads (CNW Group/Artemis_Gold Inc.)Ball Mill Shell and Heads (CNW Group/Artemis Gold Inc.)

Ball Mill Shell and Heads (CNW Group/Artemis Gold Inc.)

Artemis Gold is making significant progress on the Blackwater Mine project and is advancing toward its operational readiness. Construction activities are in full swing, with various components reaching key milestones as evidenced by successful installations of major plant equipment and structural elements. As the Company remains fully funded and on schedule, the focus in the coming months will be on completing the remaining construction elements efficiently to meet the timeline for the first gold pour in H2 2024.

Share30Tweet19
kent-jackson

kent-jackson

Recommended For You

Couple accused of scamming $4 million from women in supposed gold mine ownership scheme, authorities report

by kent-jackson
October 31, 2024
0
Couple accused of scamming $4 million from women in supposed gold mine ownership scheme, authorities report

COLORADO SPRINGS, Colo. (KKTV/Gray News) - A couple was placed behind bars in Lee County, Florida, this week after officials say they defrauded two women in Monument, Colorado,...

Read more

West Red Lake Gold Announces Latest News on Madsen Mine Reopening

by kent-jackson
October 31, 2024
0
West Red Lake Gold Announces Latest News on Madsen Mine Reopening

VANCOUVER, British Columbia, Oct. 31, 2024 (GLOBE NEWSWIRE) -- West Red Lake Gold Mines Ltd. (“West Red Lake Gold” or the “Company”) (TSXV: WRLG) (OTCQB: WRLGF) is pleased...

Read more

Today’s Gold and Silver Prices as of 31-10-2024: Find the Latest Rates in Your City

by kent-jackson
October 31, 2024
0
Today’s Gold and Silver Prices as of 31-10-2024: Find the Latest Rates in Your City

Gold and Silver Prices Today: Gold prices saw a slight increase on Thursday. The cost of 24 carat gold is Rs.8134.3 per gm, up by Rs.710.0. The cost...

Read more

Golden Fields: Latest News, Sports Updates, and Job Opportunities

by kent-jackson
October 31, 2024
0
Golden Fields: Latest News, Sports Updates, and Job Opportunities

Provided by Frank Swain Golden rod fills a field with color near Dexter City recently. If you have a recent photo that showcases the beauty of the Mid-Ohio...

Read more

Gold prices reach all-time high level

by kent-jackson
October 31, 2024
0
Gold prices reach all-time high level

Gold prices have been hitting record highs on a consistent basis in recent times. Global Economic Uncertainty One of the key drivers behind the surge in bullion prices...

Read more
Next Post
Indigenous group in the Amazon detains 12 alleged gold miners and turns them over to Brazilian police

Indigenous group in the Amazon detains 12 alleged gold miners and turns them over to Brazilian police

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Related News

Southern California couple accused of defrauding Medicare of $6 million in gold, according to federal authorities

Southern California couple accused of defrauding Medicare of $6 million in gold, according to federal authorities

October 10, 2024
Gold prices retreat as rate-cut expectations ease, pulling back from near-record levels

Gold prices retreat as rate-cut expectations ease, pulling back from near-record levels

May 23, 2024
2024 Gold House Gala – National News Coverage of the CA 2024 Gold House Gala Event

2024 Gold House Gala – National News Coverage of the CA 2024 Gold House Gala Event

May 12, 2024

Browse by Category

  • News
El Dorado Gold

We bring you the best Premium WordPress Themes that perfect for news, magazine, personal blog, etc. Check our landing page for details.

CATEGORIES

  • News

© 2025 JNews - Premium WordPress news & magazine theme by Jegtheme.

No Result
View All Result
  • Home
  • Landing Page
  • Buy JNews
  • Support Forum
  • Contact Us

© 2025 JNews - Premium WordPress news & magazine theme by Jegtheme.

Are you sure want to unlock this post?
Unlock left : 0
Are you sure want to cancel subscription?